1. An accuracy range of -15% to + 30% for a process industry falls under which class of estimate?
2. If cumulative BCWS = 100, cumulative BCWP = 98, and cumulative ACWP = 104, the project is:
3. All of the following are conceptual estimating methodologies except
4. Which of the following progress measurement methods is suitable for activities of significant duration that are composed of easily recognized, sequential sub-activities?
5. Which of the following progress measurement techniques is suitable for activities that lack readily definable intermediate milestones and/or the effort/time required is very difficult to estimate?
6. Which of the following is not necessary to classify the estimate as per the AACEI Standard?
7. Which of the following statements is not true?
8. Of the following, comparatively, which estimate requires the least amount of effort to prepare?
9. Scenario No. CEC-C, Calculate EVM metrics for the following test problems:
- Plan at End of 2nd Quarter: Tasks 1, 3, 5, and 6 should be completed, Tasks 2 and 4 should be 96 percent complete, and Task 7 should be 51 percent complete.
- Results at End of 2nd Quarter: Tasks 1, 3, 5, and 6 have been completed, Task 2 is 50 percent complete, Task 4 has not been started, and Task 7 is 10 percent complete. $137,500 has been charged to the project.
Calculate the following values (assume that all tasks incur costs uniformly over time):

Q) project initiation, what was the total projected cost of this project (BAC)?
10. Calculate EVM metrics for the following test problems:
- Plan at End of 2nd Quarter: Tasks 1, 3, 5, and 6 should be completed, Tasks 2 and 4 should be 96 percent complete, and Task 7 should be 51 percent complete.
- Results at End of 2nd Quarter: Tasks 1, 3, 5, and 6 have been completed, Task 2 is 50 percent complete, Task 4 has not been started, and Task 7 is 10 percent complete. $137,500 has been charged to the project.
Calculate the following values (assume that all tasks incur costs uniformly over time):

Q) On the status date, what is the budgeted cost of work scheduled (PV)?