Skip to content
3FOLD Training
  • Home
  • About Us
  • Courses
    • AACE
      • Certified Cost Professional
    • ASQ
      • Certified Manager of Quality
      • Certified Six Sigma Green Belt
      • Certified Six Sigma Black Belt
    • CQI IRCA
      • ISO 9001:2026 QMS Lead Auditor
      • ISO 14001:2026 EMS Lead Auditor
      • ISO 27001:2022 ISMS Lead Auditor
      • ISO 45001:2018 OHSMS Lead Auditor
    • GBCI
      • LEED Green Associate
      • LEED Accredited Professional
      • LEED GA & AP (BD+C) Combo
    • PMI
      • Project Management Professional
    • Transition
      • ISO 9001:2026 Transition
      • ISO 14001:2026 Transition
  • Schedules
  • Articles
  • Testimonials
  • Webinars
  • Contact us
Community Join 3FOLD Training Schedules on WhatsApp — get every course batch update first 3FOLD Training Schedules on WhatsApp Join now

UAE +971 50 481 9989 | India +91 91762 57536

online@3foldtraining.com
3FOLD Training3FOLD Training
  • Home
  • About Us
  • Courses
    • AACE
      • Certified Cost Professional
    • ASQ
      • Certified Manager of Quality
      • Certified Six Sigma Green Belt
      • Certified Six Sigma Black Belt
    • CQI IRCA
      • ISO 9001:2026 QMS Lead Auditor
      • ISO 14001:2026 EMS Lead Auditor
      • ISO 27001:2022 ISMS Lead Auditor
      • ISO 45001:2018 OHSMS Lead Auditor
    • GBCI
      • LEED Green Associate
      • LEED Accredited Professional
      • LEED GA & AP (BD+C) Combo
    • PMI
      • Project Management Professional
    • Transition
      • ISO 9001:2026 Transition
      • ISO 14001:2026 Transition
  • Schedules
  • Articles
  • Testimonials
  • Webinars
  • Contact us

LEED AP BD+C Practice Questions: Materials and Resources

September 3, 2026 Posted by 3FOLD No comments

Welcome to the LEED AP BD+C  practice quiz. Enter your details, then work through all 13 questions — we'll email you the score and a full explanation for every question.

1. Which material is NOT one of the six streams a project must provide dedicated storage and collection for under Planning for Zero Waste Operations?

2. A project is located in a municipality with no organics hauling service of any kind. The owner proposes to omit an organics storage area and instead direct occupants to place food waste in the commingled recyclables bin. How does this affect the waste prerequisite?

3. Which statement correctly describes what Quantify and Assess Embodied Carbon requires?

4. A team has produced a bill of materials listing quantities and A1–A3 global warming potential for every required material type in the structure, enclosure and hardscape. What must the team still deliver to satisfy the embodied carbon prerequisite?

5. A salvaged steel frame recovered from another site is incorporated into a project that is running a whole-building life-cycle assessment. How is that frame treated?

6. An existing building has 50,000 square feet of floor area. A structural engineer deems 10,000 square feet of it unsound and it is removed from the calculation. The team retains 26,000 square feet of existing structure and enclosure, and incorporates reused structural and enclosure material brought in from off site equivalent to a further 2,000 square feet. What existing building reuse percentage does the project demonstrate?

7. During demolition a project recovers 40 tons of sound face brick and sells it to an off-site architectural reclamation yard. Under which Materials and Resources item does that tonnage count?

8. In the building reuse calculation, which retained element does NOT count toward the reused area?

9. A New Construction project verifies that more than 90 percent of its paints and coatings and more than 90 percent of its flooring meet the emissions criteria, along with more than 90 percent of its insulation and more than 85 percent of its adhesives and sealants. Its ceilings reach 88 percent. What is the outcome under Low-Emitting Materials?

10. A millwork supplier furnishes documentation showing that its composite wood casework complies with the CARB airborne toxic control measure for composite wood products. Is that sufficient for the composite wood category under Low-Emitting Materials?

11. A ceilings category totals 5,000 square feet across four products: 1,000 square feet with a multi-attribute score of 3, 1,500 square feet with a score of 2, 500 square feet with a score of 4, and 2,000 square feet with no qualifying attributes. What is the category adjusted value?

12. A project generates 1,000 tons of construction and demolition material and diverts 780 tons of it. Of the diverted tonnage, 140 tons were salvaged or source-separated to single-material recyclers. What does the project achieve under Construction and Demolition Waste Diversion?

13. A project generates 1,000 tons of construction and demolition material. It source-separates 250 tons to single-material recyclers and sends the remaining 750 tons to a mixed waste processing facility that advertises a 70 percent recovery rate but holds no third-party verification of it. What diversion rate may the project claim?

clock.png

Time's up

No comments
0

Leave a reply Cancel reply

COURSE ENQUIRY FORM



    Contact us on WhatsApp

    Recent Posts

    • Life Cycle Perspective in ISO 14001:2026 Explained
    • Can ISO 14001 Help with ESG Reporting?
    • What are the steps in an ISO 45001 audit?
    • Who Should Take the ISO 45001 Lead Auditor Course?
    • Why the PMP® Exam Emphasizes the Business Environment: What PMI Expects From Project Managers

    3FOLD Training

    Your Ultimate Resource for Professional Certification and Qualifications.

    Contact us on WhatsApp

    Head Office

    3FOLD Training FZE
    1003, Park Avenue, Dubai Silicon Oasis, Dubai.
    +971 4 5776146+971 50 4819989
    online@3foldtraining.com

    Branch Office

    • 3FOLD Training
    • Plot No: 1342, HIG, TNHB Main Road, Sithalapakkam, Chennai – 600126.
    • +91 91762 57536

    SUPPORT

    Enquiry
    Contact Us
    Certificate Registry
    Privacy Policy
    Refund and Cancellation Policy
    Terms and Conditions

    © 2026 · 3FOLD Training FZE. All rights reserved

    Learn. Certify. Advance.

    Advance your career with globally recognized certifications

    • PMI Authorized Training Partner
    • CQI IRCA Approved Training Partner
    • AACEI Approved Education Provider
    30,000+ learners · 100+ countries · 4.9★ from 1,400+ Google reviews

    Get course details and expert guidance

    Ask about fees, syllabus, eligibility and the certification path

      Chat on WhatsApp

      We respect your privacy. No spam. Your details are safe with us.

      WhatsApp
      Hello, welcome to 3FOLD!
      How can we assist you?
      Open chat